Cave Creek's Phoenix Water Interconnect: What Changes Next?

Every glass of water from the Town of Cave Creek's system starts at the Central Arizona Project canal at Deer Valley Road in Phoenix. From there the untreated water is pumped about 12 miles through pipelines to the Town's treatment plant on Basin Road, where it is filtered and treated before it reaches roughly 2,500 connections. That has been the only route for drinking water on the Cave Creek system since the Town bought the Cave Creek Water Company in March 2007.

A second route is about to open. The Town expected treated water from Phoenix to start flowing through the new Phoenix Interconnect in early November. The new pipe solves the problem of how water gets to Cave Creek. It doesn't touch the problem of how much water Cave Creek can count on. That second problem is the reason the Town spent the summer taking bids from buyers interested in its water and wastewater systems.

Why one pipeline was a problem

The old setup was fragile for a simple reason. Each part had to work for water to come out of the tap. A Town solicitation from August 2019 described a system that depended on untreated CAP water pumped through a 12-mile pipeline and four booster stations to a single treatment plant. The same document listed aging treatment filters, an emergency filter media replacement in 2018, and interim membrane units with a combined 2 million gallons per day of capacity, measured against a maximum daily demand of 2.8 MGD.

Here is how the two routes compare once the interconnect is live:

  1. The original route. Cave Creek's CAP water leaves the canal at Deer Valley Road, travels about 12 miles through a 16-inch line, and is treated at the Town's 3 MGD plant on Basin Road.
  2. The new route. Cave Creek sends its own CAP water to Phoenix, Phoenix treats it, and the drinking water comes back through the interconnect. In Foothills Focus, Mayor Robert Morris described the plan as "sending Cave Creek CAP water to Phoenix; they will treat it for us." The connection can deliver up to 1.4 MGD.

In other words, Phoenix is not handing Cave Creek new water. The water is still the Town's CAP allocation. What changes is that it now has a second place to be treated and a second way into town. The 2019 solicitation also described an emergency option under the Phoenix agreement for up to 60 days of supply. In its October announcement, the Town said the finished site "will greatly enhance the reliability of the Town's water supply."

Why Cave Creek Road is down to one lane

The last piece of construction sits right where most residents drive. Beginning October 26, Cave Creek Road near the interconnect site was cut to one lane in each direction for about two weeks. The contractor, MGC, is modifying the 16-inch waterline in front of the site, which the Town called "one of the final steps." Phoenix had already finished the major work south of Carefree Highway.

The project has run later than planned. The Town's July bid documents listed August 2026 as the completion date. A later answer to bidders said Phoenix would take over all domestic and fire water service south of Carefree Highway by the start of September. At that point Cave Creek was serving just three commercial properties there through six meters. The answer added that the interconnect would be ready within a few weeks after that. By late October the target was early November. The 2019 solicitation had once estimated three to five years just for Phoenix's infrastructure.

On cost, reports don't agree. City Sun Times put the Town's investment at about $15 million, and Foothills Focus reported nearly $20 million. The Town's fiscal 2025 annual financial report lists a state WIFA loan for the project. That loan had a $7.539 million balance as of June 30, 2025, a 2.967% interest rate, a $1 million forgivable portion, and a final payment date of July 1, 2053. Morris told Foothills Focus the interconnect would not directly raise rates. "That's already built into rates," he said. "We borrowed money to keep our current rates low and spread the cost over 30 years." He also warned that rates are likely to rise for other reasons. Separately, Your Valley reported a water rate increase of 6% a year for three years. It covers Cave Creek, Desert Hills and wastewater customers and was presented in January 2026.

The supply problem the new pipe doesn't fix

A second pipeline makes delivery more reliable. It does not add a single gallon. Morris put it plainly in Foothills Focus: "Cave Creek receives nearly 90% of its water from the Colorado River via the CAP." On where to find more, he said: "The fact is, there's only one supply of water out there available for purchase."

The river's numbers this fall don't help. The Central Arizona Project's conditions dashboard shows the October 2026 24-Month Study placing Lake Mead in a shortage condition, with a 1.25 million acre-foot Lower Basin reduction in calendar year 2027 and another shortage projected for 2028. A state Arizona Reconsultation Committee presentation dated August 24, 2026 put Arizona's share of the proposed reductions at 760,000 acre-feet. CAP has not published how that reduction splits among its water users. That makes Cave Creek's own 2027 cut an open question for now.

Cave Creek's CAP water comes in two priority levels. The Town's 2022 drought plan lists 2,228 acre-feet a year of municipal and industrial (M&I) water and up to 386 acre-feet a year of lower-priority agricultural (NIA) water. The Town also holds more than 3,000 acre-feet of long-term storage credits at the Agua Fria and Hieroglyphic Mountain CAP recharge sites.

Which brings the Town back to its utility sale

On July 10, 2026, the Town issued an Invitation for Bids to sell all three of its utilities, with bids due by 2 p.m. on September 10. The bid document says the Town looked at its utilities' finances "and the anticipated future water resource needs for these systems" before deciding to test whether another public or private operator "would be better suited to address the long-term needs of these customers." Of the Town's three stated goals, two are about water supply and rates:

  • Get the highest value for the systems
  • Minimize the need for the Town to acquire new water resources
  • Reduce future rate increases for the Town's residents and businesses

Bidders had to bid on all three systems together, with a price for each one and a total.

System Accounts Where the water comes from
Cave Creek Water 2,574 metered accounts in Town and adjacent unincorporated areas CAP surface water through the 12-mile line, plus the new Phoenix interconnect
Desert Hills Water About 1,840 accounts, outside Town limits Three groundwater wells plus treated CAP water sent over from Cave Creek
Cave Creek Wastewater 947 accounts in Town Treatment plant at 44th Street and Carefree Highway, which sends A+ reclaimed water to the Rancho Mañana golf course

Any buyer would also get the Town's help transferring its CAP subcontracts, along with whatever storage credits are still unused at closing. The interconnect is part of what's for sale.

The Town's council voted unanimously in March to widen the bid from Desert Hills alone to all three systems. It also hired the consulting firm Raftelis for up to $114,000 to handle appraisals and analyze the bids. Your Valley's account of that meeting gives the mayor's view in his own words:

"Municipalities do not sell water systems. It's usually the other way around. They usually buy them. So anyone that has the idea that this is a done deal and just because we're out here doing these things, I personally am skeptical."

That came from Your Valley's report. In the same remarks Morris added, "I know we (Cave Creek) can run a water system, I know we can do it well."

What has to happen before ownership changes

The September 10 deadline has passed. Neither the September 15 nor the October 20 council agenda included a sale item. Public comments at council meetings this fall have opposed a sale, with speakers citing local control and the Town's reserves.

The bid document lays out two possible paths, depending on an official appraisal of the systems' real property:

  • Appraised at $15 million or more. The sale needs approval from Town voters at a special election, which the document expects to be held in 2027. If voters approve, the Town may then sell the systems at public auction under a term sheet every bidder must meet.
  • Appraised below $15 million. The council can approve the sale by resolution after at least one public hearing.

The bid document notes the real property "may be valued at $15,000,000 or more," but the official appraisal will decide which path applies. This post describes the Town's published process as general information. It is not legal advice, and the Town Clerk's office can answer specific questions about any election.

In the meantime, the Phoenix-treated water the Town expected in early November is still the Town's own CAP allocation, arriving by a second route.

If you own property here, or in our other market around Bellevue, the source of your water and the company that runs it are part of what your home is worth. Jennifer Rogers follows changes like this one and can explain what they mean for your address. Start with a home valuation built on current Cave Creek facts.

Expert Guidance, Exceptional Outcomes

With a focus on Scottsdale, AZ, and Bellevue, WA, Jennifer Rogers combines her extensive market knowledge with a refined approach to real estate, delivering exceptional outcomes for her clients. Discover why so many clients trust Jennifer with their most important real estate decisions and experience the difference for yourself.